Full Refurbishment - Old Hall Tavern Pub

Client

Star Pubs

Location

Chingford

Duration

4 weeks

Value

£25,000

Krypton undertook a full refurbishment of the Old Hall Tavern pub in Chingford within a four-week period to allow Star Pubs to open up to the public as soon as possible. 

Project Profile

The works involved removal of furniture and floor finishes before we undertook mechanical and electrical works and reinstalled the floor, wall and ceiling finishes. We also undertook a sympathetic restoration package to the bar joinery and cornicing within the building.

Whilst we were progressing with the internal fit out works, Krypton also undertook façade restoration works to prevent water ingress issues followed by decorations and LED lighting upgrades. 

Challenge & Solution

Prior to commencement onsite, we held meetings with the client  to review the scope and ensure early procurement orders were placed with key supply chain members, allowing us to fast track our programme to meet the client requirement. We also worked closely with the council to ensure our façade restoration works did not impact their highways. 

See More Like This ....

Full Refurbishment - Old Hall Tavern Pub

Client

Star Pubs

Value

£25,000

Duration

4 weeks

Location

Chingford

Krypton undertook a full refurbishment of the Old Hall Tavern pub in Chingford within a four-week period to allow Star Pubs to open up to the public as soon as possible.

Project Profile

The refurbishment involved a full internal strip-out followed by a comprehensive package of mechanical, electrical, and decorative upgrades. Works included the installation of a new fire alarm system, plumbing upgrades to restore running water, new sanitaryware in both WCs, and the fitting of 10 new internal doors.


We also installed a new cellar cooling unit to maintain correct barrel storage temperatures and applied decorative upgrades throughout, including a scaffold board fascia to the bar front.

Externally, Krypton undertook roof replacement works and associated variations to ensure the building envelope was fully watertight and compliant. 

 

Challenge & Solution

With a tight reopening deadline, early planning and coordination were essential. Krypton held pre-start meetings with the client to confirm sequencing, prioritise procurement, and align key trades for concurrent working. Close collaboration between site teams and suppliers allowed us to accelerate delivery without compromising quality.

 

Through proactive communication and structured management, the project was completed on time and handed back ready for reopening.

 